for this type of question, i would suggest you use the options you have as mcq instead of doing it all by yourself.
a. if purchased all:
A= (21$+11) x 5,000 = 160,000
B= (42$+20) x 6,000 = 372,000
C= (39$+17) x 3,000 = 168,000
Total= 700,000$
Note that the fixed OH is unavoidable.
b. if manufactured all:
A= 26$ x 5,000 = 130,000
B= 54$ x 6,000 = 324,000
C= 52$ x 3,000 = 156,000
Total= 610,000$
*option b is less costly than option a, but we are not able to continue with option b since we have a limited capacity of machine hours for model A and Model B. To check for how many hours constitutes each model we do the following:
Model A= 5$/unit divided by 2.5$/hr = 2hrs/unit x 5,000 units = 10,000 hrs for model A (2.5$/hr times X = 5$/unit; where X would be hr/unit)
Model B= 10$/unit divided by 2.5$/hr = 4hrs/unit x 6,000 units = 24,000 hrs for model B (2.5$/hr times X = 10$/unit; where X would be hr/unit)
Total of hrs A+B= 34,000 hrs which is higher than 28,000 hrs
c. if 5,000 units A manufactured and 4,500 units B manufactured => 1,500 units B purchased:
A= 130,000
B= (4,500 x 54$) + (1,500 x 42) = 306,000
Total= 436,000$ + 156,000$(C) = 592,000
d. if 2,000 units A manufactured => 3,000 units A purchased and 6,000 units B manufactured:
A= (2,000 x 26$) + (3,000 x 21$) = 115,000
B= 324,000
Total= 115,000 + 324,000 + 156,000 = 595,000
C is the correct answer since it gave us the least costly value out of all 3 options
------------------------------
Michel Joseph Christian Mitri
Accountant
Kornet Chehwan
Lebanon
------------------------------
Original Message:
Sent: 09-12-2020 03:21 AM
From: Phuc Ngo Mai Thien
Subject: 2C Decision analysis: Make or buy
Can anyone guide me how to solve this, please? Thanks in advance
211. CSO: 2C2d LOS: 2C2n
Synergy Inc. produces a component that is popular in many refrigeration systems. Data on three of the five different models of this component are as follows.
Synergy applies variable overhead on the basis of machine hours at the rate of $2.50 per hour. Models A and B are manufactured in the Freezer Department, which has a capacity of 28,000 machine processing hours. Which one of the following options should be recommended to Synergy's management?
a. Purchase all three products in the quantities required.
b. Manufacture all three products in the quantities required.
c. The Freezer Department's manufacturing plan should include 5,000 units of Model A and 4,500 units of Model B.
d. The Freezer Department's manufacturing plan should include 2,000 units of Model A and 6,000 units of Model B.
Correct answer c. The option (a) of purchasing externally is more costly the manufacturing internally, because Fixed OH costs are not avoidable. The option (b) is not possible due to the capacity restrictions. This leaves options (c) and (d), with option (d) being more costly than (c).